Facility: 2MW leased space, single tenant, eastern Oregon
Utility: Pacific Power, substation at 85% nameplate before we moved in
Current draw: 1.7MW sustained
Problem: applied for 3MW upgrade in March 2025. Quoted 18 months. Now August 2026. New quote: "2027 Q2 at earliest, possibly 2028." Transformer lead times are 52 weeks minimum, utility staffing is the actual bottleneck.
Options evaluated:
- Portable substations: $800K for 6-month rental, insurance won't cover
- Load shedding: already running non-critical racks on timers
- Alternative utility: 23 miles to nearest different substation, fiber chase required
Actual question: has anyone successfully negotiated with a rural utility for expedited service? What levers exist beyond "we will move"? Our lease has 4 years remaining, moving is theoretically possible but BGP sessions and RPKI ROAs for ou